Aug 2, 2024
Renovation Project Look-Ahead: Week of
Ongoing Work: 1st Floor D Wing: Electrical work continues. Mezzanine A Wing: Sprinkler installation is ongoing. Mezzanine: Continuous...
aohnotify
Jul 26, 2024
Construction Look-Ahead, Week of 7/29/24
Continue electrical work on the 1st floor D wing Sprinkler work on the Mezzanine Plumbing work ongoing on the Mezzanine Electrical work...
aohnotify
Jun 28, 2024
Project Look Ahead Week of 7/1/24 Including Important Notice
Notice: On MONDAY NIGHT, 7/1/24, FROM 7PM TO 10PM There will be a Planned Full Building Water Shutdown for Necessary Plumbing...