Mar 8, 2024
Project Look Ahead, Week of 3/11
Continue Plumbing work on 1st floor and Mezzanine wing A & C Localized water shutdown on 1st floor C wing ( Hot Water Only )Wednesday or...
aohnotify
Mar 5, 2024
Project Activities Look-Ahead for week of 3/4
Continue Plumbing work on Mezzanine ( wings A & C ) 1st Floor C wing (LVC) Abatement work in ceiling Monday & Tuesday A & C wing core...
aohnotify
Feb 28, 2024
Project Activities This Week
The renovation project is making good progress! Continue Plumbing work on Mezzanine 1st Floor C wing (LVC) ceiling openings for plumbers...