Construction Project Look-Ahead Week of 4/28/25
- aohnotify
- Apr 28
- 1 min read
PLEASE NOTE; We will be closing off part of the employees cafeteria (by the couch area) one day next week for a period of time. I will post a notice 24 hours in advance.

1st floor D wing sprinkler work continues
1st floor framing inspection on Tuesday
1st floor electric and low voltage continues
1st floor plumbing and HVAC continues
1st floor window opening at end of D wing
2nd floor framing inspection on Tuesday
2nd floor sprinkler inspection on Thursday
2nd floor plumbing and HVAC continues
2nd floor electrical and low voltage continues
If you have any questions on this posting, please call me at 914-255-7576
Richie