top of page
Writer's pictureaohnotify

Look Ahead, Week of 1/14

As we step into the next week, our project team remains committed to making steady progress on the renovation project. The week starting January 14, 2024:


  • Our team will continue with the framing work on the mezzanine level across all wings.

  • Ceiling Closure in the First Floor Library and Card Room

  • Core Drilling in A Wing for Mezzanine Level Bathrooms

  • Exploratory Work Near the Vending Area

  • Abatement Work on the First Floor Ceiling

39 views
bottom of page