Project Activities Look-Ahead for week of 3/4

  • Continue Plumbing work on Mezzanine ( wings A & C )

  • 1st Floor C wing (LVC) Abatement work in ceiling Monday & Tuesday

  • A & C wing core drilling Mezzanine Wednesday

  • Localized Water shutdowns on 1st floor C wing only, Wednesday, Thursday and Friday.

  • Electricians continue on Mezzanine,

  • Carpenters continue framing on Mezzanine

  • HVAC mechanical continue to work on Mezzanine


If you have any concerns related to project activities, please contact: Rich Felipe at 914-255-7576


Thank you