Project Activities This Week

The renovation project is making good progress!


  • Continue Plumbing work on Mezzanine

  • 1st  Floor C wing (LVC) ceiling openings for plumbers ( Monday, Tuesday and Wednesday)

  • Abatement work in ceiling 1st floor C wing ( LVC ) Thursday or Friday

  • Electrical work continuing on Mezzanine

  • HVAC Contractor continue work on Mezzanine


We had a planned water shutoff yesterday evening to accommodate certain work being performed by the contractors. We did communicate this planned shut off on the electronic bulletin board in the lobby (it is dedicated to project communications)-- and other communications. That said, we admittedly fell short of our own standards for providing more communications for this event and for that we apologize, we will do a better job the next time this occurs.


Thank you for your support and understanding as we continue to modernize our building.