Sprinkler work continues on the Mezzanine
Electrical work continues on the Mezzanine
Mechanical work continues on the Mezzanine
Carpenters continue framing and Sheetrocking on the Mezzanine
Window installation continues on the Mezzanine, Stay Alert on Sidewalks in Marked Areas!
2nd floor D wing safety disconnect continue
Monday 6/3/24 on 2nd floor initial work begins in walled off area
If you have any questions or concerns please contact, Richard Felipe, Director of Capital Projects at: 914-255-7576