Project look-Ahead for the week of 8/25/2025

Below is the project look- ahead for the week of 8/25/2025

 

  • Mezzanine punch list continues

  • 1st floor D wing Flex room windows completion this week.

  • 1st floor furniture delivery on Monday 8/25/2025

  • 2nd floor all trades on going

  • 2nd floor furniture delivery on Monday 8/25/2025

  • 2nd floor New patio door installation on Wednesday 8/27/2025

  • 2nd floor All doors  delivery this week

  • 2nd floor mill work delivery this week

 

         

If you have any questions on this posting, please call me at 914-255-7576