Project look-Ahead for the week of 8/25/2025
- aohnotify
- Sep 2
- 1 min read
Below is the project look- ahead for the week of 8/25/2025
Mezzanine punch list continues
1st floor D wing Flex room windows completion this week.
1st floor furniture delivery on Monday 8/25/2025
2nd floor all trades on going
2nd floor furniture delivery on Monday 8/25/2025
2nd floor New patio door installation on Wednesday 8/27/2025
2nd floor All doors delivery this week
2nd floor mill work delivery this week
If you have any questions on this posting, please call me at 914-255-7576
Richie