Project Look-Ahead, Week of 5/23/25:
- aohnotify
- May 23
- 1 min read
** ALL CONSTRUCTION PROJECTS ON MONDAY 5/26 CLOSED FOR MEMORIAL DAY !
Please note:
1) A portion of the cafeteria continues to be closed
2) Potential for Mezzanine conference room A to be closed for electric work
3) Potential for Mezzanine conference room B to be closed do to plumbing work for 2nd floor

4) Potential 2nd floor rotunda work by elevator and A wing construction wall for Med Gas
Mezzanine punch list continues
1st electrical and low Voltage continues
1st HVAC and plumbing continues
2nd floor HVAC and plumbing continues
2nd floor electrical and low voltage continues
2nd floor bathroom tile begins
Med gas electric and exhaust begins
If you have any questions on this posting, please call me at 914-255-7576
Richie