The renovation project is moving forward and remains on track. To keep everyone safe, some areas have been temporarily closed or restricted. Your safety is our top priority, so please stay aware of your surroundings.
Sprinkler work on Mezzanine B wing ongoing
Sprinkler B wing testing this week
Mechanical work ongoing, line sets and drain lines being run D wing, C wing will be next
Carpenters continue to frame and tape sheetrock
Window installers back on Monday for last windows on Mezzanine and to measure 2nd floor
Abatement work on 2nd floor Tuesday or Wednesday for one side of the corridor
1st floor Plumbing exploring and disconnects in D wing