The renovation project is moving forward and remains on track. To keep everyone safe, some areas have been temporarily closed or restricted. Your safety is our top priority, so please stay aware of your surroundings.


  • Sprinkler work on Mezzanine B wing ongoing

  • Sprinkler B wing testing this week

  • Mechanical work ongoing, line sets and drain lines being run D wing, C wing will be next

  • Carpenters continue to frame and tape sheetrock

  • Window installers back on Monday for last windows on Mezzanine and to measure 2nd floor

  • Abatement work on 2nd floor Tuesday or Wednesday for one side of the corridor

  • 1st floor Plumbing exploring and disconnects in D wing



If you have any questions, please call Rich Felipe at 914-255-7576