top of page

Project Look-Ahead for the Week of February 5, 2024

Project Update for the Week of February 5, 2024

  • Continuing with the Mezzanine framing in all wings, ensuring steady progress.

  • Sheetrock is set for delivery on Monday, with installation beginning on one side of the Mezzanine walls immediately.

  • Electricians are slated to start their work on the Mezzanine this week.

  • Plumbing efforts will proceed with core drilling in wings A & B, alongside necessary piping work in those areas.

  • The 1st Floor ladies' restroom will be available over the weekend (February 3-4), but please note it will be closed on Monday and Tuesday (February 5-6).



We are continuing to make progress on this important project!

31 views
bottom of page