Please note: 1) A portion of the cafeteria will continue to be closed
2) Roof penetration on the cafeteria will start on Tuesday 13th for duct work

1st floor D wing sheetrock continues
1st floor sprinkler work continues
1st floor electric and Low Voltage continues
1st floor plumbing and HVAC continues
1st floor window opening at the end of D wing
1st floor A wing HVAC , plumbing and electrical work
2nd floor plumbing and HVAC continues
2nd floor electrical and low voltage continues
2nd floor sheetrock continues
If you have any questions on this posting, please call me at 914-255-7576